    High-Rise PEB RFQ and Quote Comparison Checklist

    Prepare a high-rise PEB fabrication RFQ with a common design basis, quantity rules, shop inspection records, delivery lots and a bid comparison table.

    Author
    Kothari Chemicals (Engineering Division)
    Published
    Published: 23 November 2026
    Reading time
    5 min read
    Built-up steel members in the fabrication shop

    A useful high-rise PEB request for quotation (RFQ) lets every supplier price the same steelwork. For multi-storey buildings, the difference between two offers often comes from which drawings they price, which connections and finishes they include, and where their delivery responsibility ends. Give suppliers a common tender package and ask for line-by-line exclusions and assumptions.

    Issue the design information suppliers need

    Start with the site, building use, storey and zone sequence, structural grid and floor levels. Include the general arrangement, framing plans and sections, material grades, connection details available at tender and a current bill of quantities. Issue a drawing register with revision and status. List information that is still preliminary, such as façade reactions, service openings or steel-to-core connection details.

    Ask each bidder to name the information it needs before releasing material and before starting fabrication. Agree who can answer technical questions and how instructions will be recorded. If you need an early price while parts of the design are open, identify the affected zones and request stated allowances and a method for valuing later changes.

    Make the responsibility schedule part of the RFQ

    Tender itemWhat to ask each supplier to state
    Engineering and detailingWho owns structural design, connection design, model updates, coordination and drawing approvals
    Shop steelworkThe included columns, beams, bracing, splices, base plates, connection steel and miscellaneous items
    Floor and façade interfacesWho supplies deck, studs, edge steel, façade brackets, steel-to-core embeds and related hardware
    Inspection and coatingsThe included inspection stages and reports, coating system, finish repairs and fire protection boundaries
    Freight and site handlingDelivery point, packing, shipping lots, unloading, crane access, laydown and responsibility at receipt
    Erection and temporary worksWho provides the erection plan, site survey, temporary stability measures, field work and handover records

    Indicate the review dependencies for each lot. A release can depend on approved connection details, anchor surveys or an agreed dispatch sequence. Include the required dates for those decisions in the tender, so bidders can flag the dependencies in their programmes.

    Compare the quantity and price on a common basis

    Require each bidder to state how it measures steel for billing. Define how the tender treats plates, stiffeners, small fittings, bolts, studs and temporary attachments. Ask for a quantity breakdown by item or zone, any separately priced work and the procedure for approved additions and omissions. Compare like-for-like totals using the agreed measurement rules. The steel fabrication tonnage guide shows a worked example of a quantity adjustment.

    For example, suppose Bid A quotes the frame and connection plates, coats the members and delivers by floor. Bid B includes those items plus shop-installed studs and a specified set of bolts, with delivery to a staging yard. Ask for separate prices for the studs, bolt set and onward transport as applicable. Confirm whether each delivery plan meets the erection team's requirements. Then compare the total for the same delivery point, scope and dates.

    Ask for a workable inspection and delivery plan

    List the inspection and test plan requirements, required witness points, welder and procedure records, material certificates, dimensional checks, coating records and release documentation as applicable. Define who reviews each submission and how a nonconformance is resolved. Ask for a sample index of the records that will accompany each dispatch, so the receiving team knows what to expect. See the hold, witness and review point guide.

    Assign a delivery lot to each erection zone or floor group. Ask bidders for the anticipated largest pieces, how they will be identified, how loose items will be grouped, and any restrictions on maximum piece size or shipment sequence. Give them site access and unloading constraints early. Do the same review for work arriving from other contractors, especially deck, embeds and anchor assemblies.

    Use a short bid review before award

    1. Confirm the baseline. Check revisions, quantities, fabrication boundaries and major technical assumptions.
    2. Resolve exclusions. Put a named party and price against every excluded item needed for the frame or delivery.
    3. Check the programme. Compare design release, material procurement, first dispatch and the delivery sequence by zone.
    4. Agree records. Confirm inspection sign-offs, packing lists, drawing history and the handover package.
    5. Close open items. Record pending information, approval dates and the commercial process for later changes.

    Frequently asked questions

    What can I send for a budget quote?

    Share the latest framing plans, structural sections, preliminary member quantities, project location, intended scope and major delivery constraints. Ask the bidder to identify assumptions and the information needed to convert the estimate into a firm offer.

    When should the fabrication schedule start?

    Ask the supplier to state when procurement and shop production start for each release. Tie those dates to the required approvals and information, then record them against the delivery sequence in the quotation.

    For a package review, see our high-rise PEB manufacturing capability or send the RFQ and drawing register.

    • high-rise PEB
    • PEB RFQ
    • steel fabrication quotation
    • phased dispatch
    • procurement

    About Kothari Chemicals (Engineering Division)

    The Kothari Chemicals (Engineering Division) at Kothari Chemicals (Engineering Division) writes from day-to-day work in steel fabrication, quality assurance and project execution at the Bhilai works.

    Enquiries

    Send your drawings for a technical review.

    Share drawings, specifications, quantities and delivery requirements. Our engineering team reviews scope, inspection needs and schedule before quoting.

    Works & sales
    +91 788 2974 016
    Hours
    Mon–Sat, 9:00–18:00 IST
    Works
    Plot No. 3, Heavy Industrial Area, Hathkhoj, Bhilai 490026, Chhattisgarh, India