    Kharsia–Gurda Case Study: Fabricating 700 MT of Railway Girders

    How Kothari Chemicals fabricated and delivered 700 MT of steel truss and plate girders to BBJ for the Kharsia–Gurda railway bridge in Chhattisgarh.

    Author
    Kothari Chemicals (Engineering Division)
    Last updated
    Last updated: 23 November 2026
    Reading time
    4 min read
    Kharsia–Gurda Case Study: Fabricating 700 MT of Railway Girders

    Kothari Chemicals (Engineering Division) fabricated and delivered 700 metric tonnes of steel truss and plate girders for a major railway bridge between Kharsia and Gurda in Chhattisgarh. The girders formed part of a new broad-gauge electrified double-line railway. The fabrication package for BBJ Construction included drawing review, fabrication, inspection, trial assembly, coating and dispatch. BBJ accepted the delivered package.

    Project snapshot

    ItemProject details
    ProjectMajor railway bridge between Kharsia and Gurda, Chhattisgarh
    ClientThe Braithwaite Burn and Jessop Construction Company Ltd. (BBJ)
    Supplied steelworkSteel truss girders and plate girders
    Fabricated quantity700 metric tonnes
    OutcomeDelivered and accepted

    The 700-tonne figure covers Kothari's fabrication package and is listed in the company's executed-work register. BBJ's public tender document gives the wider context for the bridge works on the South East Central Railway section.

    From drawing review to trial assembly

    Drawing review and fabrication

    The team reviewed the drawings and package requirements before production and fabricated the truss and plate girders to the project drawings. The two girder types give a reviewer different interfaces to look at. A steel truss transfers loads through connected chords and web members, so the connection geometry matters to how the assembly fits together. A plate girder uses a web plate and flanges, with stiffeners and other details as shown on the drawings. Its fabrication review typically focuses on section dimensions, alignment and splice details.

    For a similar package, share the member schedule, drawing revisions and connection details at enquiry stage. That gives the fabricator a basis for planning production and identifying the interfaces that will need to be checked together.

    Inspection and non-destructive testing

    Inspection and non-destructive testing (NDT) were part of the package. For a comparable enquiry, ask for an inspection plan that connects each required check to a member, weld or assembly and identifies the record that will show its release. If the client or inspecting agency must witness a stage, put that requirement in the plan before the shop fixes its production schedule.

    Trial assembly

    Trial assembly gave the team a shop-stage check of the relevant interfaces before shipment. On a railway girder package, an assembly record can capture how mating members align, whether connection holes line up and how the measured geometry compares with the drawings. Where the project specifies camber, record the support and measurement conditions so the reading can be interpreted against the correct reference. The RDSO sample quality assurance plan shows how trial-assembly checks can be documented.

    Steel truss girder and crew at the works for the BBJ bridge package

    Coating, dispatch and acceptance

    The fabricated steelwork was coated and dispatched to BBJ. The package was delivered and accepted. On a similar project, ask the fabricator to tie each member mark to the assembly drawing and packing list so the receiving team can identify mating pieces and check that connection items arrive with the correct load. Agree on the coating release records and shipment sequence while planning site receipt.

    What to include when requesting a comparable package

    • Drawings and member schedule. Include current revisions, member marks, approximate weights and the scope of supply.
    • Shop inspection requirements. Identify the applicable specifications, inspecting authority, witness stages and reports required for release.
    • Trial assembly requirements. Specify the assemblies to demonstrate, the governing drawings and the dimensional records to submit.
    • Delivery requirements. State the coating system, delivery point, desired shipment sequence and site unloading constraints.

    See the guides to trial assembly and camber checks and long girder transport planning for more detail. Compare other fabrication projects or share your drawings and delivery requirements for a quote.

    Frequently asked questions

    What does the 700-tonne figure cover?

    It is the executed-work quantity for the steel truss and plate girders supplied by Kothari Chemicals to BBJ for the Kharsia–Gurda bridge package.

    What work did Kothari carry out?

    The package covered drawing review, fabrication, inspection and NDT, trial assembly, coating and dispatch of the girders. BBJ was the client for that supply package.

    • Kharsia-Gurda
    • railway bridge
    • steel truss girders
    • plate girders
    • BBJ Construction

    About Kothari Chemicals (Engineering Division)

    The Kothari Chemicals (Engineering Division) at Kothari Chemicals (Engineering Division) writes from day-to-day work in steel fabrication, quality assurance and project execution at the Bhilai works.

    Enquiries

    Send your drawings for a technical review.

    Share drawings, specifications, quantities and delivery requirements. Our engineering team reviews scope, inspection needs and schedule before quoting.

    Works & sales
    +91 788 2974 016
    Hours
    Mon–Sat, 9:00–18:00 IST
    Works
    Plot No. 3, Heavy Industrial Area, Hathkhoj, Bhilai 490026, Chhattisgarh, India